Westland Beach project progresses; county receives related shoreline grants

LANCASTER—During the Lancaster board of supervisors meeting on Thursday, October 31, assistant county administrator John Bateman reported progress continues on Phase 1 of Westland Beach at Windmill Point, involving the rebuilding of the beach and construction of a pier.

Four of seven breakwaters are complete and pilings for the pier have been installed, said Bateman. Phase 1 is expected to be completed in April.

Phase 2, to follow, involves construction of a parking lot and bath house. County administrator Don Gill said the project will go out to bid in January, with a 180-day projected construction window beginning….

There's more to this story...
Are you a subscriber? 

 Log in

Many more news articles, photos and ads are available only to those
who
subscribe to our printed newspaper or our online e-Edition.

Pick up a copy or Subscribe today!

Follow us on Social Media

Visit our Advertisers

Your Local Weather

Kilmarnock
clear sky
74.7 ° F
79.9 °
70.7 °
56 %
1.6mph
0 %
Thu
76 °
Fri
77 °
Sat
71 °
Sun
61 °
Mon
58 °